Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

ms project training courses - percentage complete

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training courses - Percentage complete

ms project training courses - Percentage complete

ResolvedVersion Standard

Ava has attended:
Project Intro Intermediate course

Percentage complete

I have added a black line in the task bar to show how much is completed. Is it possible to add %complete as a viewable figure next to the bar

RE: percentage complete

use the tracking gantt to view this data

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back