I have a report to draft which I have entered as one task. How do I allocated people to that task but not on an equal basis, i.e.
Work
Drafting Allan 30 hours
Checking Joe 7.5 hours
Duration
4 weeks to draft the report
RE: Resources & Time
Joe
Use the resource usage sheet for individuals and their times.