microsoft project training - Milestones

ResolvedVersion Standard

Vanessa has attended:
Project Intro Intermediate course

Milestones

Does the milestone have to be related to what date and time it is supposed to be achieved?

RE: Milestones

VAnessa

A milestone is a deliverable, which must be reached before the next stage of the project can go forward.

regards

david

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.