ms project training courses london - Sharing Resources in Project

ResolvedVersion Standard

William has attended:
Project Intro Intermediate course

Sharing Resources in Project

Is there a way not only of seeing the tasks that the resources are allocated to in the shared file (which I can) but also the titles of the other projects (which I can't)?

RE: Sharing Resources in Project

Not to my Knowledge

RE: Sharing Resources in Project

If you use the Resource Usage View then you can also insert the Project Column into this view. This allows you to see Resources, Assignments and Projects. You can also filter on this column too if you wish.

Further if you use a split view and place the Gantt Chart View in the lower half of the screen you'll be able to select a resource and see all the assignments in the Gantt Chart for that resource.

Hope that helps.

Jeff
(MS Project Consultant)

RE: Sharing Resources in Project

This is fine, Jeff- many thanks.

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.