Is it possible to use MS Project to record times worked by different contributors?

RE: Time records

Hi Chris

Thanks for your question - the answer relates directly to your other post. The Resource Usage view lets you record actual time-phased work completed (from the format menu choose Details then Actual Work)

Once you have baselined your project you can also double click tasks in this view to update actual work carried out by the resource. Although it's not quite as detailed as using the full sheet you do still get to allocate work carried out on a resource by resource basis.

If we can be of any further help please do let us know.

Kind regards,

Andrew

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.