How do assign projects to contractors?

RE: MS Project

Hi Roz

First you would build your project plan, made up of the tasks to be completed. The create your resources (contractors etc) on the resource sheet. Finally you bring them together by assigning resources to your tasks.

In the Gantt chart view choose Tools then Assign Resources... to bring up the assignment dialogue box. Click on your task then choose your resources and click on Assign.

I hope this helps - do let us know if you need further information.

Kind regards,

Andrew

RE: MS Project

The main problem I have is that contractors don't have the time constraints that exists with individuals - ie it's not my problem if they are under resourced, it is down to them to find resources. I think I will have to ignore the flag for over resourcing and just assign contractors.

Thank you for taking the time to reply to me.

Regards

Roz

RE: MS Project

Hi Roz

You're welcome. There may indeed be times when you choose to ignore overallocation warning messages. Alternatively you could set the Max Units % very high so that overallocation doesn't become an issue.

Kind regards,

Andrew

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.14 secs.