Anna has attended:
Project Intro Intermediate course

Microsoft Project

How would I mail a whole project with attachments (which are attached from my local files.)

RE: Microsoft Project

Hi Anna

Thanks for your question. From the file menu choose send to > mail recipient as attachment. Your email programme will launch with a copy of the project file attached to the message. Because the documents you inserted into Project are local to that file they will also be included in the Project attachment.

Hope this helps, let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.