Work times

how do I put the resource where I have something that will take 2 days in duration but only takes 2 hours in total in those days?

RE: work times

Hi Jill

Try this - create your task and set it to a two day duration. Insert the Work column and specify that it has 2 hours of work. Then finally assign your resource.

Hope this helps, let us know if you would like any further information.

Kind regards,

Andrew

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.11 secs.