ms project training - link

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training - Link

ms project training - Link

resolvedResolved · Low Priority · Version Standard

Jatinder has attended:
Project Intro Intermediate course

Link

How do i create a start to start link?

RE: Link

Hi Jatinder,

Thanks for the question

On the View menu, click Calendar.
Hold down CTRL, and click each task you want to link.
Click Link Tasks .

Once you have created the link you can then double click on it and change it to Start to Start using the drop down box.

Hope that helps

Tracy


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.07 secs.