courses microsoft project london - Constraints

ResolvedVersion Standard

Debi has attended:
Project Intro Intermediate course

Constraints

Hi,

Is there a quick way of removing all constraints on a plan I have without removing each one individually?

Many Thanks

Debi

RE: Constraints

Debi

Click on any field heading, this selects all the tasks under that field, goto the multiple task information box and select the advanced tab, in the empty constraints box, from the drop down selct as late or as early as possible, this will reset your constraints and take out any constraint identifiers from the ID field

regards

dave