RAG Status Based on Finish Date
custom field formula required to calculat the RAG based on finish date
RE: RAG Status Based on Finish Date
Hi Julia,
I assume you are comfortable with setting up Custom Fields
The formula you need is
IIf([Baseline Finish]-[Finish]>=5,"Green",IIf([Baseline Finish]-[Finish]>=0,"Yellow",IIf([% Complete]>0,"Blue","Red")))
I've used Baseline Finish because I want to RAG it based on the agreed dates (Baselined) vs the current plan in Project.
You could use the [Start] or [Current Date] fields instead.
The next step is to set up "Values to Display"
Graphical Indicators.
Test
Equals
Values
Red Yellow Green Blue
Image
Choose the Coloured circles to match
I hope that helps
Kind regards
Richard Bailey