microsoft project courses london - Constraint Times

ResolvedVersion Standard

Natasha has attended:
Project Intro Intermediate course

Constraint Times

If I had an event date already decided, how could i put this in the gantt chart without making many contstraints?

RE: Constraint Times

Hi Natasha

Thanks for your question. Your task will need a constraint of some kind if you are working to a specific date. Project would prefer your constraints to be partial (such as start no earlier than) rather than full (must...)

The remaining tasks can be left with no constraint so that Project is able to calculate your dates for you.

I hope this helps - do let us know if you have any other questions.

Kind regards,

Andrew

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.