How do you program dates so that it works out 'working days' only. In law we have to use 'clear days' for service which means 3 days becomes 5.
RE: Dates
Hi Roxanna,
Thank you for the forum question.
Please have a look at attached workbook. I am using the Networkdays function. You will need to have a list of all the UK bank holidays in your workbook as well to get the right result.
Kind regards
Jens Bonde
Microsoft Office Specialist Trainer