98.8% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Professional and Management support » Andrew
Andrew
Resolved · Low Priority · Version Standard
James has attended:
Project Management - Framework & Processes course
Excel Introduction course
Andrew
Please tell me more about earn value?
RE: Andrew
Hi James
Thank you for your question. Earned value is based on simple values - such as:
Budgeted Cost of Work Scheduled (BCWS) - our budget (or baseline)
Budgeted Cost of Work Performed (BCWP) - the agreed resource rate applied to work carried out
Actual Cost of Work Performed (ACWP) - what we really paid for the work carried out.
With these figures we can work out :
Performance Index:
BCWP/ACWP = CPI or Cost Performance Index. Less than 1 the project is over spending
BCWP/BCWS = SPI or Schedule Performance Index. Less than 1 means the project is behind schedule.
Here are two Microsoft resources on Earned Value:
http://office.microsoft.com/en-au/project-help/about-earned-value-analysis-HP001034258.aspx
http://office.microsoft.com/en-au/project-help/applying-earned-value-analysis-to-your-project-HA001021179.aspx?CTT=3
I hope this is helpful - do let me know if you have any further questions.
Kind regards,
Andrew
Wed 4 Jul 2012: Automatically marked as resolved.
Training information:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
Management Training tip:Task List or To Do ListDon't confuse yourself with too many tasks on a to do list. The Task List is all the things that require attention, whether by you or others, now or later. The To Do list is your immediate daily plan, and is a subset of your Task List. |