Please tell me more about earn value?

RE: Andrew

Hi James

Thank you for your question. Earned value is based on simple values - such as:

Budgeted Cost of Work Scheduled (BCWS) - our budget (or baseline)
Budgeted Cost of Work Performed (BCWP) - the agreed resource rate applied to work carried out
Actual Cost of Work Performed (ACWP) - what we really paid for the work carried out.

With these figures we can work out :

Performance Index:
BCWP/ACWP = CPI or Cost Performance Index. Less than 1 the project is over spending

BCWP/BCWS = SPI or Schedule Performance Index. Less than 1 means the project is behind schedule.

Here are two Microsoft resources on Earned Value:

http://office.microsoft.com/en-au/project-help/about-earned-value-analysis-HP001034258.aspx

http://office.microsoft.com/en-au/project-help/applying-earned-value-analysis-to-your-project-HA001021179.aspx?CTT=3

I hope this is helpful - do let me know if you have any further questions.

Kind regards,
Andrew

Wed 4 Jul 2012: Automatically marked as resolved.

 

Training courses

Training information:

Welcome. Please choose your application (eg. Excel) and then post your question.

Our Microsoft Qualified trainers will then respond within 24 hours (working days).

Frequently Asked Questions
What does 'Resolved' mean?

Any suggestions, questions or comments? Please post in the Improve the forum thread.

Management Training tip:

Task List or To Do List

Don't confuse yourself with too many tasks on a to do list. The Task List is all the things that require attention, whether by you or others, now or later. The To Do list is your immediate daily plan, and is a subset of your Task List.

Keep your To Do list to no more than 5 major items.

View all Management Training hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.