98.8% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project 2003 training - Placing meetings into the project plan
microsoft project 2003 training - Placing meetings into the project plan
Resolved · Low Priority · Version Standard
Tasfin has attended:
Project Intro Intermediate course
Placing meetings into the project plan
How do I place meetings that occur once every three months on to the project plan. I want to place the meetings as a task, but have one task punctuated throughout the project plan with that meeting being held once every three months.
RE: Placing meetings into the project plan
Hi Tasfin
Thank you for your question.
You can reschedule recurring meetings by going to Insert - Recurring tasks in the Gantt chart view.
I hope this answers your question.
Amanda
RE: Placing meetings into the project plan
Hello Tasfin,
Coming to the query. I think you can Create recurring tasks using Gantt Chart.
Support link for this query to help is - https://support.microsoft.com/en-us/office/create-recurring-tasks-88a4d903-38c3-4665-870e-4810b752f2c4
Hope this helps you.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |