we are trying to print a cash flow from MS Project but some of the taskes are not shown just a series of lines. How can we print the whole project. Thanks Simon Turoff

RE: MS Project

Hi Simon

Thank you for your question. You mention printing a cash flow from Project. Are you using the Cashflow report (Project > Reports > Costs > Cashflow? Also are the tasks displayed correctly on screen in the view you are using and Project is not formatting the printing correctly?

Let me know how you are producing the data in Project and I will try and help you.

Kind regards,
Andrew

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips