Lucy has attended:
Project Intro Intermediate course
Calendars
Are there any definitive rules for where a calendar should be changed to ensure it will apply to a particular resource?
RE: Calendars
Hi Lucy
Probably the most straightforward way to adjust a calendar that affects a particular resource is to go to the resource sheet and double click the resource in question. From the resource information dialogue box choose the Working Time tab. From here you can adjust the calendar for the resource directly.
If you have any further questions please let us know.
Kind regards,
Andrew