microsoft-project-training - views

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft-project-training - Views

microsoft-project-training - Views

resolvedResolved · Low Priority · Version Standard

Gladstone has attended:
Project Intro Intermediate course
Project Advanced course
Excel Introduction course
Excel Intermediate course

Views

How do I customise my views

RE: Views

Hi Gladstone

You can go to View > More views... and from the list that appears select the view you wish to modify then click on the edit button.

Hope this helps - let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.08 secs.