Is there any possible way to link an ongoing excel holiday sheet to the change working time calander?

My problem is that I do not deal with staff leave but I would like to keep an up to date holiday calander.

If you have any advice I would be most grateful.

Many Thanks

RE: Holiday Calander/Change working time

Hi Jen,

Thank you for your question.

Unfortunately I am not aware of a method to do this.

You can copy other data directly from excel to Project such as resource and task information.

Sorry I couldn't have been of more help.

Regards

Simon

Thu 9 Dec 2010: Automatically marked as resolved.


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.08 secs.