How do you import muliple projects on a single master project and still can still use all resources for any task?

RE: MS Project

Hi Chris,

Thank you for your question.

Open up a new Project and click into the first available task name field. Go to the Project tab and click on the first button on the ribbon which is SubProject. Choose the first project and it adds it on task ID 1. Move to the task ID 2 and keep repeating the procedure until all the projects are in.

By default the individual projects will be automatically linked to the master project.

If you have the resources ready then you can start assigning them to all the tasks in the master project.

I hope this answers your question.

Regards

Simon

Thu 9 Dec 2010: Automatically marked as resolved.

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.