RE: Project Plan

Hello Madeline,

Hope you enjoyed your Microsoft Project Intro Intermediate course with Best STL.

Thank you for your question regarding how to set up a new project plan.

This question is too broad to be answered here in full. First of all the planning stage of a project is not usually performed using MS Project software. This is carried out after a series of meetings are held where details of the project are identified and recorded for later input into MS Project. i.e. Project stages/phases, tasks, milestones etc.

The preferred step-by-step setup is as follows:
Go to File Properties > Create title for your project > OK
Save the file
Create a company calendar > add this to the Global.mpt file
In the Project menu go to Project information
Select start date for your project
Select company calendar from the drop-down list > OK
Right-click the Gantt chart area select Non-Working Time
Select company calendar from the drop-down list > OK
In the Task Name column of the Entry Table
Enter summary tasks
Insert sub-tasks making sure to indent them correctly
Add durations
Link tasks as required
Create resources in the Resource Sheet
Assign resources to each task
Change task types if necessary
Change predecessor if necessary
Add deadline dates if required
Add constraints if required
Show the Critical path using the Gantt Chart Wizard
Set the baseline > Save

Now you are good to go!



I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

Fri 26 Nov 2010: Automatically marked as resolved.

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)