Forum home » Delegate support and help forum » Microsoft Project Training and help » MSP2003 Resource View

MSP2003 Resource View

ResolvedVersion 2003

Anthony has attended:
Project Intro Intermediate course
Project Advanced course
Excel Advanced course
Excel Advanced course

MSP2003 Resource View

Hi

QUESTION: in Resource View. Is there a way to alter the units to 'days' and back ?

Back ground info:

My MSProject Resource view I am able to change all the data and fields in the left pane (Resource names and tasks etc).

My problem is my Right pane. it shows the hours for the day/week. against each resource/task.

My standard is 7.5 hours per day.

this is a drama as I have 2 MSP plans from different project teams, One allocate tasks in days (or decimal fractions of days) and the other uses hours.

I need to assess my utilisation of my resource pool manually split in 2 silos (we are not lucky enough to have a shared resource pool as one project worked off a different computer network - if only !).

RE: MSP2003 Resource View

FOUND IT !

In the tier selection and options. Choose the option to display Days or hours.

Sorted !

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.