msp resource view

Forum home » Delegate support and help forum » Microsoft Project Training and help » MSP2003 Resource View

MSP2003 Resource View

resolvedResolved · High Priority · Version 2003

Anthony has attended:
Project Intro Intermediate course
Project Advanced course
Excel Advanced course
Excel Advanced course

MSP2003 Resource View

Hi

QUESTION: in Resource View. Is there a way to alter the units to 'days' and back ?

Back ground info:

My MSProject Resource view I am able to change all the data and fields in the left pane (Resource names and tasks etc).

My problem is my Right pane. it shows the hours for the day/week. against each resource/task.

My standard is 7.5 hours per day.

this is a drama as I have 2 MSP plans from different project teams, One allocate tasks in days (or decimal fractions of days) and the other uses hours.

I need to assess my utilisation of my resource pool manually split in 2 silos (we are not lucky enough to have a shared resource pool as one project worked off a different computer network - if only !).

RE: MSP2003 Resource View

FOUND IT !

In the tier selection and options. Choose the option to display Days or hours.

Sorted !


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.07 secs.