Hi
QUESTION: in Resource View. Is there a way to alter the units to 'days' and back ?
Back ground info:
My MSProject Resource view I am able to change all the data and fields in the left pane (Resource names and tasks etc).
My problem is my Right pane. it shows the hours for the day/week. against each resource/task.
My standard is 7.5 hours per day.
this is a drama as I have 2 MSP plans from different project teams, One allocate tasks in days (or decimal fractions of days) and the other uses hours.
I need to assess my utilisation of my resource pool manually split in 2 silos (we are not lucky enough to have a shared resource pool as one project worked off a different computer network - if only !).