ms project training in london - Assigning Resources
Resolved · Low Priority · Version Standard
Kevin has attended:
Project Intro Intermediate course
Assigning Resources
When assigning resources to a task where I am putting more than one individual resource to each the task duration isnt calculating as expected. It works when I change units per resource but i wont be able to do that if i was using individual names.
RE: Assigning Resources
Try going to tools then Options and select the Schedule tab
make sure Effort driven is ticked in the middle of the Schedule tab and fixed units is selected try this first
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |