ms project training in london - Assigning Resources

ResolvedVersion Standard

Kevin has attended:
Project Intro Intermediate course

Assigning Resources

When assigning resources to a task where I am putting more than one individual resource to each the task duration isnt calculating as expected. It works when I change units per resource but i wont be able to do that if i was using individual names.

RE: Assigning Resources

Try going to tools then Options and select the Schedule tab
make sure Effort driven is ticked in the middle of the Schedule tab and fixed units is selected try this first

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.