Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project splits task when assigning resource

MS Project splits task when assigning resource

ResolvedVersion 2007

Balint has attended:
No courses

MS Project splits task when assigning resource

Hello,

I am working on MS Project Server 2007.
When I assign a resource to a task, MS Project splits it and I have to manually fix all tasks by dragging.

I was working with another file last week and everything was going well.

What is going wrong?

RE: MS Project splits task when assigning resource

Hi Balint

Thank you for your question.

The split that Ms Project creates could be caused by your resource having non-working time in their calendar that requires the task to be delayed. If part of the task has been marked as complete then MS Project will split it - leaving the completed work unchanged in the schedule but the unfinished work will be delayed until the Resource next has available working time.

Let us know if you are still having problems with this and we can try and track the cause down.

Kind regards,
Andrew

Thu 8 Apr 2010: Automatically marked as resolved.

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.