ResolvedVersion 2007

Mo has attended:
Project Intro Intermediate course

Calendars

How can myself and my collegue use the same calendar.

RE: Calendars

Hi Mo,

Thank you for your question and welcome to the forum.

Unfortunately I do not know of a way to share your calendar with other colleagues without using Project Server or some sort of add or plug-in.

Regards

Simon

Wed 17 Feb 2010: Automatically marked as resolved.

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips