how to print a particular summary task including its subtasks only

RE: printing

Hi Timea,

Thank you for your question.

If you insert a text 2 field and device a set of identical text for each group:
Tasks Text 2
-----------------------------
Phase 1 PH1
Task A PH1
Task B PH1
Phase 2 PH2
Task C PH2
TasK D PH2

Now hide that column field.

Then go to Project - Filtered For and More Filters. Click New.

Set the FieldName to Text 2, then the Test box to Equals and in the Value(s) box type "Please enter Phase code"?

Whenever you run that filter a prompt box will come up with the speech marked text. If you type PH1 it should return the summary task and sub tasks.

If you wanted the results to print for multiple phases add the same criteria to the row or rows below but change the And/Or column to OR between each line of criteria.

I hope this works. Let me know.

Regards

Simon

RE: printing

Thanks Simon, that works. Timea

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.