critical paths

Forum home » Delegate support and help forum » Microsoft Project Training and help » Critical paths

Critical paths

resolvedResolved · Low Priority · Version 2007

Alexandra has attended:
Project Intro Intermediate course

Critical paths

How is the critical path calculated and how can I see it?

RE: Critical paths

Hi Alex

Thank you for your question.

The Critical Path in MS Project identifies those tasks that dictate when your plan will finish. They have no Slack which means if they change (duration, delay) your end date will also change.

You can quickly see the Critical Path by switching to the Tracking Gantt view (View > Tracking Gantt). Critical tasks are highlighted in red.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Tue 29 Dec 2009: Automatically marked as resolved.


 

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips


Server loaded in 0.08 secs.