Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

updating work done

Forum home » Delegate support and help forum » Microsoft Project Training and help » Updating work done

Updating work done

ResolvedVersion 2007

Piers has attended:
Project Intro Intermediate course

Updating work done

i have a nightmare trying to account for work done each day on a task. A task might be only a day long but could easily be done in hourly bits over a few days, but to account for this always seems to go wrong!

RE: updating work done

Hi Piers

Thank you for your question. It sounds like you might have one day of Work to be carried out over several days of duration. You may find it easier to update your tasks by either Switching to the Resource Usage view then right clicking on the right hand table. From the menu that appears you will see an option to display Actual Work. Selecting this allows you to record what really took place, day by day. Project will adjust the Duration to reflect the changes you make.

Alternatively in the Gantt Chart view you may prefer to add the Actual and Remaining Work columns and progress your tasks that way.

Let me know how you get on and if you have any further questions.

Kind regards,
Andrew

RE: updating work done

Thank you Andrew. The issue is usually with the way that updating actual work seems to keep throwing the duration and % complete values out completely, but I figured from the course that I just need to ignore this value ... would this be right?

RE: updating work done

Hi Piers

Thanks for coming back to me. Rather than ignore it I think maybe see it for what it is i.e. % duration complete. It's likely that you'll be more focussed on tracking actual work and remaining work.

Let me know how you get on.

Kind regards,
Andrew

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.13 secs.