ms project and project management training london - linked projects

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project and project management training london - Linked Projects

ms project and project management training london - Linked Projects

resolvedResolved · Low Priority · Version Standard

Linked Projects

If I link a number of different projects and save them in a 'Master File' could I sort the projects within a file by date?

RE: Linked Projects

Yes you can go to project on the menu bar then sort by start date


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.07 secs.