Tansy has attended:
Project Intro Intermediate course
Print report by finish date
Hello
I wanted to find out how to print a report by the task finish date. The idea being that I could print a report for "all tasks with a finish date of next week" - and then I would spend the week beforehand following up with everyone and making sure they are on track to finish their tasks next week!
Can you please advise what report/parameters I would need to enter (and into where) to get this report?
thanks and kind regards
Tansy
RE: Print report by finish date
In the report select Current Activities then select Tasks Starting Soon
RE: Print report by finish date
Go to View on then Reports then select Current Activities then select Tasks Starting Soon
RE: Print report by finish date
What ever date you put in the current Activities then it will print upto that date