Forum home » Delegate support and help forum » Microsoft Project Training and help » Split usage

Split usage

resolvedResolved · Low Priority · Version 2003

Richard has attended:
Project Intro Intermediate course

Split usage

How to achieve

RE: split usage

Hi Richard

Can you tell me more about what you are looking to achieve so I direct you further?

Tasks can be split by choosing Edit > Split task then hovering over the bar to be split. In the tool tip that appears you will see the date where you are about to make your split. Left click and drag to the right then let go. Project will split your task.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Fri 30 Oct 2009: Automatically marked as resolved.


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Server loaded in 0.07 secs.