Slipping taks

How do you update tasks that have slipped

RE: Slipping taks

Hi Bridget thank you for your question.

You can click on the task then from the Tools > Tracking menu choose Update Task. You can use the dialog box that appears to record actual work and remaining as well as actual start (and finish) information. Project will then redraw the task to reflect what took place.

I hope this helps do let us know if you have any further questions.

Kind regards,
Andrew

Fri 30 Oct 2009: Automatically marked as resolved.

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.36 secs.