Printing

How best to display the key tasks and milestones for project. Maybe with ability to include in a slideshow.

RE: Printing

Hi Andrew,

Thank you for your question.

You could create a custom filter to show the Summary tasks and Milestone tasks.

Then copy and paste special into a PowerPoint slide or use the Copy Picture technique and save it as a GIF image and then insert the picture into the slide.

I hope this answers your question.

Regards

Simon

Tue 6 Oct 2009: Automatically marked as resolved.

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips