Task Information

resolvedResolved · Medium Priority · Version 2007

Richard has attended:
Project Intro Intermediate course

Task Information

What does the priority in the Task Info \ General mean?

RE: Task Information

Hi Richard

Priority is used to give weighting to tasks as part of the leveling process (Tools > Level resources). Tasks with higher priorites (up to 1000) are not delayed whereas lower priority tasks are pushed back to deal with overallocation of resources.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Wed 26 Aug 2009: Automatically marked as resolved.


 

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.