How do you show the critical tasks?

RE: Critical tasks

Hi Meredy

Thank you for your question. A quick way to see the critical tasks in your plan is to swith to the Tracking Gantt view. You can do this from the View menu. Critical tasks will be coloured red.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Thu 6 Aug 2009: Automatically marked as resolved.


 

MS Project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips