Critical tasks
How do you show the critical tasks?
RE: Critical tasks
Hi Meredy
Thank you for your question. A quick way to see the critical tasks in your plan is to swith to the Tracking Gantt view. You can do this from the View menu. Critical tasks will be coloured red.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew