Graham has attended:
Project Intro Intermediate course
Filter for % progress
can you apply filter out completed activities
RE: filter for % progress
Hi Graham
Thank you for your question - yes you can. From the Project menu choose Filtered for > Incomplete tasks.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew