Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

filter progress

Forum home » Delegate support and help forum » Microsoft Project Training and help » Filter for % progress

Filter for % progress

ResolvedVersion 2007

Graham has attended:
Project Intro Intermediate course

Filter for % progress

can you apply filter out completed activities

RE: filter for % progress

Hi Graham

Thank you for your question - yes you can. From the Project menu choose Filtered for > Incomplete tasks.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Thu 6 Aug 2009: Automatically marked as resolved.

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips

Connect with us: