Are you able to change the colours of bars to show correlations with other tasks

RE: Critical Path

Hi Simone

Thank you for your question. You can format the bars by either double clicking the bar or by highlighting several tasks and choosing Format > Bar from the menu. This lets you format the shape and colour of the bar.

Format > Bar styles lets you set the style for existing and new objects in your chart.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Progress To Date & Drop Line

Hi,

I am currently working in Project 2007 and I have managed to fill in the progress to date on all of my tasks (ie. the black line across the bar) and then I have placed a progress line on this programme as well. My problem comes in the fact that I can get the progress line to point right to the items that I am lagging on - however it wont point left to the items that I am ahead of schedule on. I have tried everything I even read the Project for Dummies book but have had no luck yet in figuring it out. Can you please help me?

Many thanks
Simone

Thu 6 Aug 2009: Automatically marked as resolved.

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)