baseline vs actuals

Forum home » Delegate support and help forum » Microsoft Project Training and help » Baseline vs. Actuals

Baseline vs. Actuals

resolvedResolved · High Priority · Version 2003

James has attended:
No courses

Baseline vs. Actuals

Progress lines to compare the progress

RE: Baseline vs. Actuals

Hi James,

Thank you for your question.

Are you using Progress lines to compare the progress?

You should be using the Tracking table in Gantt chart view to enter actual Start and Finish dates. Tyou can compare the actual plan to the baseline.

If so, go to Tools, Tracking and then Progress lines. In the bottom right of the dialogue box, make sure the 'Display progress lines in relation to baseline plan' checkbox is selected and not the actual plan.

I hope this answers your question.

Regards

Simon

Fri 7 Aug 2009: Automatically marked as resolved.


 

MS Project tip:

Using the Quick Access Toolbar in Project 2010

The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010.

You will find the Quick Access Toolbar in the top-left side of the window. To begin, click the Customize button (it's the little black arrow at the end of the toolbar).

Simply click the commands you want to include.

Virtually any command can be added to the Quick Access Toolbar. Click the More Commands option and a new window will open from where you can browse the commands including those not on the ribbon.

View all MS Project hints and tips


Server loaded in 0.05 secs.