Project Intro Intermediate course

Milestones

how do I move milestone dates on gantt chart?

RE: milestones

Hi Cath,

Thank you for your question and welcome to the forum.

You can hover over the Milestone marker and drag it to a date in the future. Project will add a Start no earlier than constraint.

However, it is unlikely you would do this. Milestone tasks are usually linked to a predecessor task which means that if the predecessor task changes the milestone date would automtically update.

I hope this answers your question.

Regards

Simon

Thu 2 Jul 2009: Automatically marked as resolved.

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.