Milestones

resolvedResolved · Low Priority · Version 2007

Cath has attended:
Project Intro Intermediate course

Milestones

how do I move milestone dates on gantt chart?

RE: milestones

Hi Cath,

Thank you for your question and welcome to the forum.

You can hover over the Milestone marker and drag it to a date in the future. Project will add a Start no earlier than constraint.

However, it is unlikely you would do this. Milestone tasks are usually linked to a predecessor task which means that if the predecessor task changes the milestone date would automtically update.

I hope this answers your question.

Regards

Simon

Thu 2 Jul 2009: Automatically marked as resolved.


 

MS Project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.05 secs.