Costs

How do I generate my overall cost for a project?

RE: Costs

Hi Patrick,

Thank you for your question.

There are many answers to this question.

If you add the Project summary task to the Project and then change the table applied to the Gannt Chart to the Cost Table.

Now you will see the Total Cost field and the total cost for the Project Summary task.

Another way of achieving this is to go to the Project menu, Project Information and then Statistics.

I hope this answers your question.

Regards

Simon

Thu 2 Jul 2009: Automatically marked as resolved.

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)