project.training - Milestone

resolvedResolved · Low Priority · Version Standard

Sally has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Milestone

How do I create above

RE: Milestone

Sally

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Tracy


 