courses microsoft project london - MILESTONE

resolvedResolved · Low Priority · Version Standard

PETER has attended:
Project Intro Intermediate course
Project Intro Intermediate course

MILESTONE

HOW DO I CREATE THE ABOVE

RE: MILESTONE

Peter

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Tracy


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.