Forum home » Delegate support and help forum » Microsoft Project Training and help » london course ms project - Milestone

london course ms project - Milestone

ResolvedVersion Standard

Rossana has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Milestone

how do I create a milestone

RE: milestone

Rossana

Thanks for the question

Enter a zero 0 day in the duration part of the task

Good luck

Tracy

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips