Project

How do I clear multiple deadlines in one go?

RE: Project

Hi Mark,

Thank you for your question.

Select the desired tasks first and click the Task Information button on the toolbar or choose Task Information from the Project menu.

Go to the Advanced Tab and type NA in the Deadline box.

I hope this answers your question.

Regards

Simon

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips