Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project training in london - Time Periods

microsoft project training in london - Time Periods

ResolvedVersion Standard

Matthew has attended:
Excel Intermediate course
Excel Advanced course

Time Periods

Can you please let me know if it is possible to create a programme using hours as a timeline rather than days? (ie) for a short term project over 5 days with multiple tasks that require 10 or more tasks to be completed within a day.

When using the timeline as days I know you can reduce the period to complete to 0.25 days but this is not very visually effective when printed.

RE: Time Periods

YES
On the Tools menu, click Options, and then click the Schedule tab.
Under Scheduling options for, in the Duration is entered in list, click a duration unit.
To use the same setting automatically in all future projects, click Set as Default.

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.