If I wish to enter new tasks in sections of a file already set-up by someone else, because a project manager now wants extra tasks or wants greater detail, will Project automatically make the necessary links with the existing tasks?

RE: Microsoft Project

Hi Mark

Thank you for your question and welcome to the Forum.

By default MS Project has a setting switched on that tries to auto link inserted tasks. Generally this is not very helpful as the links created are not based on the task logic but always default to Finish to Start. The setting can be turned off by going to Tools > Options > Schedule and removing the tick from Auto link inserted or moved tasks.

Generally it's more reliable to manually link inserted tasks to make sure they follow the logic you require rather than a default Finish to Start.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

RE: Microsoft Project

Morning Andrew

I just wanted to say that the 2 day MS Project course I attended this week was excellent and the best IT training course I have attended.

I will certainly be putting my newly acquired skills into practice later this week!

Many thanks

Kind regards

Mark

RE: Microsoft Project

Hi Mark

Thank you for your feedback - much appreciated. All the best with MS Project and let us know if you have any questions when you start to put things into practice.

Kind regards,
Andrew

MS Project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.1 secs.