what is teh difference between physical percentage and complete percentage?

RE: percent complete

Hi Nancie,

Thank you for your question. This is not an easy question to answer with a small explanation.

I have found a link to a website with a description of the differences between these two fields.

http://www.mpug.com/News/Pages/TrackProjectProgresswithPhysicalComplete.aspx

I hope this is helpful to you.

Regards

Simon

Thu 9 Apr 2009: Automatically marked as resolved.

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.