Percent complete

Which is the best choice to complete percent complete? Physical, work or percentage to show 100% complete or does it matter?

RE: Percent complete

Hi Nancie,

Thank you for your question.

When you update a value in the Actual work column it will calculate the % work complete. There is no best answer as each of these methods can used in different situations.

The following link gives you an insight to what these methods are used for.

tp://www.mpug.com/News/Pages/TrackProjectProgresswithPhysicalComplete.aspx

I hope this helps.

Regards

Simon

Thu 9 Apr 2009: Automatically marked as resolved.

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.