ResolvedVersion 2003

S has attended:
Project Intro Intermediate course

Resources

how do i link internal and external resources

RE: resources

Hi S

Thank you for your question

Can you clarify your question for me. In particular;

1. Do you wish simply to distinguish between internal and external resources in your resource sheet?
2. If so do you wish to reflect the cost of using these resources?


Regards

Stephen

Mon 30 Mar 2009: Automatically marked as resolved.

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)