changing dates

Forum home » Delegate support and help forum » Microsoft Project Training and help » Changing dates

Changing dates

resolvedResolved · Low Priority · Version 2003

Changing dates

How do i move all the dates forward in a project by say 3 months when my end date changes - without losing any slack time?

RE: changing dates

Hi Claire

Thank you for your question. One way to approach this that works best when progress has not been recorded in your plan is to turn on the Analysis toolbar (View > Toolbars > Analysis) and click on the Adjust dates button then enter the new start date for your project.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes

View all MS Project hints and tips


Server loaded in 0.08 secs.